 Project Schedule
 Wastewater Treatment Plant
2000 2001 2002 2003 2004 2005 2006
Spring 2000
Preliminary
Engineering Began
           
Spring 2001
Final
Design Begins
           
Summer 2001
Construction 
Begins on Site Work
           
Fall 2003
Construction
Begins on Plant
           
Fall 2006
Plant 
Startup
           
Fall 2006
All Construction
Complete
           

 Conveyance System
2001 2002 2003 2004 2005 2006
Spring 2001
Tunnel & Lift Station
Design Start
         
Spring 2003
Tunnel & Lift Station
Design Finish
         
Winter2003
Tunnel Construction Start
         
Summer 2006
Tunnel Construction Finish
         
Summer 2004
Lift Station Construction Start
         
Fall 2006
Lift Station Construction Finish