The projects described in this section are related to constructing, rehabilitating or maintenance repair of sanitary or combined sewers, improvements to existing treatment plants, and the reduction of inflow and infiltration in the separate sewer area. These types of projects help alleviate basement backups, address regulatory issues and rebuild part of our decaying infrastructure system. Also included is the continued funding of the construction of projects related to the Lower Meramec Treatment Plant and the continued funding of a program to eliminate basement backups. Fifty-one (51) projects are to be funded at a total estimated cost of $182,620,000.
The District's revenue source for constructing the majority of these projects is obtained from the Sanitary Replacement Fund, which receives money from wastewater user charges and from the sale of revenue bonds. The remaining projects will be funded with revenues from various Operation, Maintenance, Construction, and Improvement (OMCI) Funds, Construction Funds, Special Funds, or the Improvement Fund. The property taxes collected within the boundaries of the OMCI Taxing Districts must be spent for improvements within their specific areas of collections. The Construction Fund and Improvement Fund receive revenues from various connection fees. |
|
| PROJECT
NUMBER |
PROJECT
NAME |
COST
ESTIMATE |
| 2002044B |
BISSELL POINT WWTP BELT FILTER PRESS IMPROVEMENTS PHASE III(INSTALLATION) |
$350,000 |
| 2002044A |
BISSELL POINT WWTP BELT FILTER PRESS IMPROVEMENTS
PHASE II(STRUCTURAL MODIFICATIONS) |
$300,000 |
| 2003058 |
BOENKER SANITARY RELIEF (SKME-007) |
$535,000 |
| 2000065 |
CARR STREET PUMP STATION & FORCE MAIN REPLACEMENT
(P-108) |
$600,000 |
| 2005124 |
CASTLE OAKS SANITARY SEWER |
$280,000 |
| 89130 |
CC-11 AND CC-20 CREVE COEUR CREEK SANITARY RELIEF |
$3,200,000 |
| 90012 |
CC-18 SMITH CREEK BRANCH SANITARY RELIEF (SKME-028) |
$2,000,000 |
| 90015A |
CC-22 SCHOETTLER/CLAYTON TO HWY 40 SANITARY REPLACEMENT PHASE II |
$800,000 |
| 2003103 |
CLIFTON HEIGHTS COMBINED SEWER RELIEF |
$1,700,000 |
| 99077 |
COLDWATER TREATMENT PLANT IMPROVEMENTS |
$51,000,000 |
| 2003062 |
CREVE COEUR CREEK (L-52) PUMP STATION IMPROVEMENTS |
$12,000,000 |
| 2005103 |
CSO-CLAYTON RD AND HADDINGTON CT CSO INTERCEPTOR (I-94)/OUTFALL |
$150,000 |
| 2003146 |
CSO-GREENBRIAR COMBINED SEWER SEPARATION |
$360,000 |
| 2003053A |
CSO-INTERCEPTOR & OUTFALL MODIFICATIONS
(LM-143,BP-003,BP-006,BP-019,BP-030,BP-037,BP-043) |
$4,000,000 |
| 2003054A |
CSO-INTERCEPTOR ACCESS AND MONITORING IMPROVEMENTS |
$400,000 |
|
2003054B |
CSO-INTERCEPTOR ACCESS AND MONITORING IMPROVEMENTS PHASE II |
$3,600,000 |
| 2005149 |
CSO-LARGE DIAMETER SEWER FLOWMETERS |
$400,000 |
|
2005148 |
CSO-SMALL DIAMETER SEWER FLOWMETERS |
$400,000 |
| 2003145 |
CSO-WAVERTON AND MAGNOLIA CSO INTERCEPTOR (I-179) ELIMINATION |
$890,000 |
|
2001049 |
EVA-WABASH SANITARY RELIEF PHASE I |
$2,100,000 |
| 2005125 |
FENTON WASTEWATER TREATMENT PLANT PROCESS AIR PIPING REPLACEMENT |
$75,000 |
|
88088A |
FF-02 FEE FEE -ALAN SHEPHARD I-270 SANITARY RELIEF |
$1,300,000 |
| 89137 |
FF-08 FEE FEE CREEK SANITARY RELIEF |
$4,450,000 |
|
89155A |
FF-13 WALTZ RD/MCKELVEY SANITARY RELIEF PHASE II |
$500,000 |
| 90022D |
FISHPOT EAST SANITARY RELIEF PHASE IV |
$1,800,000 |
|
2003056 |
FROST-MIDWOOD SANITARY RELIEF |
$2,200,000 |
| 2003061 |
GRAND GLAIZE WWTP IMPROVEMENTS |
$29,000,000 |
|
2003049 |
HARLEM-BADEN RELIEF PHASE V (GOODFELLOWS AND STRATFORD) |
$150,000 |
| 2003050 |
HARLEM-BADEN RELIEF PHASE V (THEODORE/ASHBY AND CORA/MARCUS) |
$650,000 |
|
93077C1 |
INFRASTRUCTURE REPAIR #087P CAULKS CREEK "A" (P-750) PHASE IV,
SECTION B |
$3,400,000 |
| 2005118 |
INFRASTRUCTURE REPAIRS (OPERATIONS-FY2006) |
$2,400,000 |
|
2005119 |
INFRASTRUCTURE REPAIRS (REHABILITATION) (FY2006) |
$5,000,000 |
| 2003078 |
LEMAY PUMP STATION NO.3 AND FORCE MAIN IMPROVEMENTS |
$11,000,000 |
|
2005092 |
LEMAY WWTP STORMWATER OUTFALL CONSOLIDATION |
$285,000 |
| 2001072A |
LINDENWOOD SEWER SYSTEM RELIEF PHASE II |
$400,000 |
|
2005120 |
MACKLIND PUMP STATION IMPROVEMENT |
$65,000 |
| 90060 |
MC-01 WEBSTER AND MARLBOROUGH TRUNK SANITARY RELIEF |
$6,450,000 |
|
99076B |
MISSOURI RIVER TREATMENT PLANT IMPROVEMENTS PHASE I(REHABILITATION) |
$5,500,000 |
| 2000045 |
NORTH PRICE TO PENNELL SANITARY REPLACEMENT |
$1,330,000 |
|
89185 |
OLD MILL CREEK SEWER REHABILITATION PHASE I- RANKEN TO 21ST STREET |
$5,500,000 |
| 2003074 |
REAV-TEL SANITARY RELIEF |
$1,000,000 |
|
2003081A |
SEPARATE SEWER AREA - INFLOW/INFILTRATION REDUCTION PROJECTS (EVA WABASH
REHABILITATION) |
$2,400,000 |
| 2005091 |
SEWER IMPROVEMENTS IN ST. LOUIS CITY PARKS PHASE III |
$660,000 |
|
2003097A |
SOUTHERN ARSENAL ORS INTERCEPTOR IMPROVEMENTS (I-203A, I-205, I-206,I-208,
I-209, I-210,I-211 , I-212) |
$250,000 |
| 2003097B |
SOUTHERN ARSENAL ORS INTERCEPTOR IMPROVEMENTS (PRESIDENT STREET AT FLOODWALL
SEWER IMPROVEMENT) |
$100,000 |
|
2003097C |
SOUTHERN ARSENAL ORS INTERCEPTOR IMPROVEMENTS (TEXAS SEWER REHABILITATION) |
$350,000 |
| 2003037 |
SPRING GARDEN-BANFF TO RIVERVIEW SANITARY RELIEF |
$1,240,000 |
|
2003088 |
TOWER GROVE-MANCHESTER COMBINED SEWER SYSTEM PHASE I |
$1,000,000 |
| 90080A |
UPPER MALINE TRUNK SANITARY RELIEF PHASE III SECTION A |
$5,400,000 |
|
2000046 |
WILLIAMS CREEK SANITARY INTERCEPTOR |
$3,700,000 |
| TOTAL |
$182,620,000 |