Project Name
|
Municipality |
Reason Continued |
Cost Est. |
| 1 |
ARBAN SANITARY RELIEF(SKME-509) (FY05) |
CRESTWOOD |
PROJECT DESIGN NOT COMPLETE(IN HOUSE).ANTICIPATE BOARD INTRODUCTION IN NOV05 |
$345,000 |
| 2 |
BISSELL POINT NATURAL GAS SERVICE REVISIONS (PHASE I) (FY05) |
ST. LOUIS CITY |
PROJECT DELAYED PENDING NEGOTIATIONS WITH LACLEDE GAS. ANTICIPATE BOARD INTRODUCTION IN APRIL 06 |
$350,000 |
| 3 |
BISSELL POINT NATURAL GAS SERVICE REVISIONS (PHASE II) (FY05) |
ST. LOUIS CITY |
PROJECT DELAYED PENDING NEGOTIATIONS WITH LACLEDE GAS. ANTICIPATE BOARD INTRODUCTION IN APRIL 06 |
$150,000 |
| 4 |
BLACKSTONE-CLARENDON COMBINED SEWER SYSTEM (DESIGN)(FY05) |
ST. LOUIS CITY |
PROJECT PRELIMINARY DESIGN NOT COMPLETE(CONSULTANT).ANTICIPATE BOARD INTRODUCTION IN FEB06 |
$1,000,000 |
| 5 |
CC-10 CREVE COEUR CREEK SANITARY RELIEF PHASE III(FY05) |
ST. LOUIS COUNTY |
PROJECT PENDING EASEMENT CONDEMNATION.ANTICIPATE BOARD INTRODUCTION IN FEB06 |
$2,950,000 |
| 6 |
CSO-INTERCEPTOR ACCESS AND MONITORING IMPROVEMENTS PHASE II (DESIGN) (FY05) |
VARIOUS |
PROJECT PRELIMINARY DESIGN NOT COMPLETE (CONSULTANT). ANTICIPATE BOARD INTRODUCTION IN JULY 05 |
$852,000 |
| 7 |
DANIEL BOONE TRUNK SEWER AND CHANNEL REPLACEMENT (PARTIAL FUNDING 564)(FY05) |
FLORISSANT |
PROJECT PENDING EASEMENT CONDEMNATION . ANTICIPATE BOARD INTRODUCTION IN MARCH06. |
$2,600,000 |
| 8 |
EASTERN ROCKY BRANCH COMBINED SEWER SYSTEM (DESIGN) |
ST. LOUIS CITY |
PROJECT PRELIMINARY DESIGN NOT COMPLETE (CONSULTANT). ANTICIPATE BOARD INTRODUCTION IN SEP 05 |
$1,000,000 |
| 9 |
FF-15 MCKELVEY/R.R. TO ADIE SANITARY RELIEF PHASE I (FY02) |
MARYLAND HEIGHTS |
PROJECT PENDING EASEMENT CONDEMNATION . ANTICIPATE BOARD INTRODUCTION IN DEC 05 |
$1,500,000 |
| 10 |
FF-15 MCKELVEY/R.R. TO ADIE SANITARY RELIEF PHASE II (FY02) |
MARYLAND HEIGHTS |
PROJECT PENDING EASEMENT CONDEMNATION . ANTICIPATE BOARD INTRODUCTION IN DEC 05 |
$2,500,000 |
| 11 |
FILLMORE COMBINED SEWER SYSTEM IMPROVEMENTS PHASE I (FY05) |
ST. LOUIS CITY |
PROJECT IN EASEMENT ACQUISITION. BOARD INTRODUCTION ANTICIPATED IN OCT 05 |
$1,400,000 |
| 12 |
GRAVOIS TRUNK (WHITECLIFF TO RDP) SANITARY RELIEF PHASE I (FY05) |
ST. LOUIS COUNTY |
PROJECT IN EASEMENT ACQUISITION. BOARD INTRODUCTION ANTICIPATED IN JUL 05 |
$5,900,000 |
| 13 |
HARLEM- BADEN PHASE IV (ROSALIE) (FY05) |
ST. LOUIS CITY |
PROJECT DESIGN NOT COMPLETE (CONSULTANT). ANTICIPATE BOARD INTRODUCTION IN MARCH 06 |
$1,900,000 |
| 14 |
HARLEM-BADEN RELIEF PHASE III(HIGHLAND)(FY04) |
ST. LOUIS CITY |
PROJECT PENDING EASEMENT CONDEMNATION . ANTICIPATE BOARD INTRODUCTION IN APRIL 06 |
$2,200,00 |
| 15 |
LACLEDE'S LANDING INFLOW REDUCTION (FRANKLIN DROP SHAFT) (FY04) |
ST. LOUIS CITY |
PROJECT DELAYED PENDING APPROVAL BYE THE CITY OF ST. LOUIS . ANTICIPATE BOARD INTRODUCTION IN AUGUST 05 |
$300,000 |
| 16 |
LOWER MERAMEC RIVER WASTEWATER TREATMENT PLANT WETLANDS MITIGATION PHASE II(FY04) |
ST. LOUIS COUNTY |
NEED FOR ADDITIONAL WETLAND MITIGATION HAS NOT BEEN DETERMINED BY THE CORP OF ENGINEERS |
$130,000 |
| 17 |
MARBENDALE - LEMP SANITARY FACILITIES CONSOLIDATION (FY05) |
KIRKWOOD |
PROJECT IN EASEMENT ACQUISITION. BOARD INTRODUCTION ANTICIPATED IN APRIL 06 |
$2,950,000 |
| 18 |
MISSOURI RIVER WWTP BIOSOLIDS REMOVAL -SOUTH LAGOON PHASE I (FY05) |
MARYLAND HEIGHTS |
DELAYED DUE TO SEASONAL CONSTRUCTION REQUIREMENTS. ANTICIPATE BOARD INTRODUCTION IN JULY 05 |
$5,000,000 |
| 19 |
OAK DRIVE TO BOPP LANE SANITARY RELIEF PHASE II (FY04) |
TOWN AND COUNTRY |
PROJECT IN EASEMENT ACQUISITION. BOARD INTRODUCTION ANTICIPATED IN SEP 05 |
$750,000 |
| 20 |
REAVIS BARSACKS & TELEGRAPH - RIDGEVIEW HILLS SEPARATE SEWER AREA I/I REDUCTION (FY05) |
ST. LOUIS COUNTY |
PROJECT DESIGN NOT COMPLETE(IN HOUSE).ANTICIPATE BOARD INTRODUCTION IN AUGUST 05 |
$353,000 |
| 21 |
REAVIS BARRACKS-REAV-TEL TO RAINBOW SEPARATE SEWER AREA I/I REDUCTION (FY05) |
ST. LOUIS COUNTY |
PROJECT DESIGN NOT COMPLETE(IN HOUSE).ANTICIPATE BOARD INTRODUCTION IN AUGUST 05 |
$655,000 |
| 22 |
RHODES AVENUE RELIEF SEWER (FY04) |
ST. LOUIS CITY |
PROJECT IN EASEMENT ACQUISITION. BOARD INTRODUCTION ANTICIPATED IN SEP 05 |
$340,000 |
| 23 |
TOWER GROVE- MANCHESTER COMBINED SEWER SYSTEM (DESIGN) (FY05) |
ST. LOUIS CITY |
PROJECT PRELIMINARY DESIGN NOT COMPLETE (CONSULTANT). ANTICIPATE BOARD INTRODUCTION IN AUGUST 05 |
$2,000,000 |
| 24 |
TOWNE SOUTH INTERCEPTOR SANITARY RELIEF PHASE II(FY02) |
ST. LOUIS COUNTY |
PROJECT PENDING EASEMENT CONDEMNATION . ANTICIPATE BOARD INTRODUCTION IN DEC 05 |
$3,000,000 |
| 25 |
UR-06 UPPER RIVER DES PERES SANITARY RELIEF PHASE II (FY05) |
VARIOUS |
PROJECT IN EASEMENT ACQUISITION. BOARD INTRODUCTION ANTICIPATED IN FEB 06 |
$2,000,000 |
| 26 |
WESTERN ROCKY BRANCH SEWER SYSTEM (DESIGN) (FY05) |
ST. LOUIS CITY |
PROJECT PRELIMINARY DESIGN NOT COMPLETE (CONSULTANT). ANTICIPATE BOARD INTRODUCTION IN SEP 05 |
$1,400,000 |
| 27 |
WILDHORSE CREEK ROAD RELOCATION (FY04) |
CHESTERFIELD |
ST LOUIS COUNTY DEPARTMENT OF HIGHWAYS AND TRAFFIC TO ADMINISTER PROJECT. PROJECT DELAYED BY COUNTY DUE TO FUNDING ISSUES. ANTICIPATE BOARD INTRODUCTION IN MARCH 06 |
$72,000 |
|
|
|
TOTAL |
$43,597,000 |