MSD Masthead Search Contact Us Job Opportunities Outreach Customer Service Programs & Projects About MSD Home Home
CIRP 2006 Infrastructure Engineering Projects

PROJECT NAME
COST ESTIMATE
BLACK CREEK WATERSHED FACILITY MAPPING VERIFICATION
$1,200,000
BRIGHTWELL SANITARY RELIEF(SKME-213) (DESIGN)
$350,000
CAPILIA SANITARY RELIEF (SKME-511)(DESIGN)
$250,000
CASTLE SANITARY RELIEF(SKME-230)(DESIGN)
$310,000
CCTV INSPECTION AND PHYSICAL INSPECTION OF SEWERS (SUPPLEMENTAL APPROPRIATION FY2006)
$2,000,000
CHAMBERS-SOUTH BENTON COMBINED SEWER SYSTEM (DESIGN)
$600,000
COLDWATER SANITARY RELIEF SECTION B, C & D (LAND ACQUISITION)
$3,000,000
COMBINED SEWER AREA - INFLOW/INFILTRATION ASSESSMENT (SUPPLEMENTAL APPROPRIATION FY2006)
$4,500,000
COMBINED SEWER AREA-FLOW METERING AND MONITORING (SUPPLEMENTAL APPROPRIATION FY2006)
$2,000,000
CSO-BREDELL AVE- WESTON PL TO ST ALBANS AVE CSO INTERCEPTOR (I-182 ,L-123) SEPARATION (DESIGN)
$226,000
CSO-BREDELL AVE AND LINDBERGH DRIVE CSO INTERCEPTOR (I-190, L-122) SEPARATION (DESIGN)
$70,000
CSO-CLAYTONIA TERRACE AND DALE AVE CSO INTERCEPTOR ( I-101A , 101B/L-126,127) SEPARATION (DESIGN)
$204,000
CSO-HAMPTON PARK AND CENTER DR 1133 CSO INTERCEPTOR/OUTFALL(I-92 , 146A/L-136, 139) STRUCTURE (DESIGN)
$136,000
CSO-HAMPTON PARK DR CSO INTERCEPTOR (I-115, L-138) SEPARATION (DESIGN)
$83,000
CSO-INTERCEPTOR AND OUTFALL MODIFICATIONS PHASE II (DESIGN)
$1,000,000
CSO-INTERCEPTOR AND OUTFALL PERFORMANCE ASSESSMENT (SUPPLEMENTAL APPROPRIATION)
$590,000
CSO-MENDELL DR-WAYNE TO MILAN DR CSO INTERCEPTOR (I-137, 166/L-100,101)STRUCTURE (DESIGN)
$613,000
CSO-MIDDLESEX AND YORK DR(L-110) SEWER SEPARATION (DESIGN)
$200,000
CSO-OLIVE AND I-170 CSO INTERCEPTOR ( I-97, L-102) /OUTFALL (DESIGN)
$680,000
CSO-PAGE AVE. OUTFALL L-167,I-296 SEPARATION (DESIGN)
$284,000
CSO-PARK DR CSO INTERCEPTOR (I-146B, L-140) SEPARATION (DESIGN)
$280,000
CSO-PARKRIDGE ADDITION COMBINED SEWER SEPARATION AND RELIEF (DESIGN )
$335,000
CSO- SHAFTSBURY AVE AND WILD CHERRY LN CSO INTERCEPTOR (I-186,178/L-094) CONSOLIDATION (DESIGN)
$453,000
DAKOTA COMBINED SEWER SYSTEM (DESIGN)
$750,000
EASEMENT ACQUISITION FOR COMBINED/SANITARY /Eng/CIRP06/Projects (FY 2006)
$1,200,000
FERRY COMBINED RELIEF (PRELIMINARY DESIGN)
$1,000,000
FILLMORE COMBINED SEWER SYSTEM IMPROVEMENTS PHASE II (DESIGN)
$300,000
FOUNTAIN/ANTHONY LATERAL SANITARY RELIEF (SKME-236)(DESIGN)
$880,000
GC-07 GRAVIOUS CREEK TO STONELL DR SANITARY RELIEF (SKME-519)(DESIGN)
$280,000
GRAND GLAIZE WWTP IMPROVEMENTS-ENGINEERING CONSTRUCTION SERVICES
$1,100,000
GRAVIOUS TRUNK (WHITECLIFF TO RDP) SANITARY RELIEF PHASE III (DESIGN)
$700,000
JEFFERSON BARRACKS PUMP STATION ELIMINATION (DESIGN)
$3.,200,000
KICKAPOO SANITARY RELIEF (SKME-518) (DESIGN)
$350,000
LEMAY WWTP WET WEATHER EXPANSION-ENGINEERING CONSTRUCTION SERVICES
$1,700,000
LOUISA COMBINED SEWER SYSTEM (DESIGN)
$500,000
LOWER MERAMEC RIVER WWTP CONSTRUCTION PHASE SERVICES- BAUMGARTNER (SUPPLEMENTAL APPROPROATION)(FY2006)
$1,450,000
LOWER MERAMEC RIVER WWTP CONSTRUCTION PHASE SERVICES-WWTP (FY2006)
$2,450,000
MIDLAND SANITARY RELIEF (SKME-226)(DESIGN)

$220,000

MISSOURI RIVER BONFILS INFILTRATION AND INFLOW CORRECTION PHASE VI (LATERAL SEWER REHABILITATION) (DESIGN)
$350,000
MISSOURI RIVER TREATMENT PLANT IMPROVEMENTS - ENGINEERING CONSTRUCTION SERVICES
$400,000
PADDOCK CREEK SANITARY RELIEF (SKME-206) (PRELIMINARY DESIGN)
$550,000
RADAR RAINFALL DATA (SUPPLEMENTAL APPROPRIATION FY2006)
$100,000
REINKE SANITARY RELIEF (SKME-407)(DESIGN)
$365,000
SEPARATE SEWER AREA -INFLOW/INFILTRATION ASSESSMENT (SUPPLEMENTAL APPROPRIATION FY2006)
$3,500,000
SEPARATE SEWER AREA FLOW METERING AND MONITORING (SUPPLEMENTAL APPROPRIATION FY2006)
$4,000,000
TAYLOR-FILLMORE-HARRISON SANITARY RELIEF (SKME-502&503) (DESIGN)
$610,000
TREATMENT PLANT CONSTRUCTION PHASE SERVICES (COLDWATER AND LEMAY)
$2,200,000
TREATMENT PLANT CONSTRUCTION PHASE SERVICES (GRAND GLAIZE AND MISSOURI RIVER)
$900,000
UR-02 RIVER DES PERES SANITARY RELIEF (DESIGN)
$400,000
UR-03 RIVER DES PERES SANITARY RELIEF PHASE II (DESIGN) (SUPPLEMENTAL APPROPRIATION)
$400,000
WATERSHED FACILITY PLANNING (SUPPLEMENTAL APPROPRIATION FY2006)
$6,300,000
WEBSTER GROVES TRUNK "E" SANITARY RELIEF (SKME-628) PRELIMINARY DESIGN)
$1,500,000
WILLIAMS AVE- BIG BEND TO BREDELL COMBINED SEWER RELIEF (DESIGN)
$130,000

TOTAL

$57,149,000

Posted 08/05

 

CAPILIA-SANITARY-RELIEF
BRIGHTWELL-SANITARY-RELIEF
CASTLE-SANITARY-RELIEF
cctv-inspection-phy-inspec-sewers
CHAMBERS-SOUTHBENTON
COMBINED SEWER AREA
COLDWATER
COMB-SEW-AREA-FLOWMETERINGnmonit
cso-bredav-WplSTalban-csoIntercepSeparation
cso-InterNOutfallModificationsPhase2
CSO-CLAYTONIAterrNdaleAv-INTER-SEP
CSO-BREDAV-LINDBERG-INTERCEPTO-SEP
cso-InterNOutfallPerformAssess
cso-MendellDr-Wayne-MilanDr-csoInterStr
cso-hamptonPkDrCsoInterSep
CSO-HamptonPkNCenterDr-inter_outfallStr
cso-olive-I170csoInter_outfall
cso-MiddleSex-yorkDrSewerSep
cso-ParkDrCSOInterSep
CSO-PageAvOutfallSep
cso-parkridgeAdditionCombSewSepnRel
GC-07-GraviousCr-StonellDrSanitRelief
Fountain-anthony-lateral-sanit-relief
easementAcquisitionCom-SanProj
cso-ShaftsburyAvNWildCherryLnInterConsol
dakota-comb-sew-Sys
FerryCombRelief-prelimdesign
FillmoreCombSewSysImpPhase2
grandGlaizeWwtpImprove-EnggConsServ
LouisaCombinedSewerSys
lemayWwtpWetWeatherExp-EngConsServ
JefferronbarrPumpStElimin
MORiverBonfilsInfilandInflowCorPhase6
PaddockCreekSanitRel
LowerMeramecRivWwtpConsPhaseSerwwtp
LowerMeramecRivwwtpConBaumgartner
MORiverTreatPLantImpEngConsServ
kickapooSanitrelief
gravoisTrunkSanRel
MidlandSanitaryRelief
ReinkeSanitRelief
UR-03RiveDesPeresSanitRelPhase2
WillAvBigbendtoBredellCombinedSewerrelief
RadarRainfallData
WatershedFacPlanSupp
separateSewerAreaFlowMeternMonitor
separateSewerAreaInflowInfilAssess
websterGrovestrunkESanitRelief
taylorFillmoreHarrisonsanitrelief
UR-02RivDesPeresSanitReli
TreatPlantConstPhaseServglaize-MOriv
TreatPlantConstPhaseServ
BLACK-CREEK-WATERSHED-FAC-MAPPING-VER