CIRP 2006 Stormwater Continued Projects

Some of the District's Stormwater projects are continued from previous fiscal years due to difficulties in easement acquisitions, the permit process from other agencies, design revisions, special requirements, or lack of funds.

There are five (5) projects that were identified in previous budget supplements that are still in the design and/or easement acquisition process. These projects have a total estimated cost of $1,991,000.

The fiscal year indicated in parentheses at the end of each project title indicates the budget year that the project was originally planned. The District's revenues to construct these projects are from the appropriate Operation, Maintenance, Construction, and Improvement (OMCI) Funds.

Listed by Municipality or Project

By Municipality
Municipality

Project

Reason Continued Cost Est.
Brentwood Eulalie Ave. 8600 Block Phase II (FY04) Project in easement acquisition. Anticipate board introduction in March 2005. $290,000
Florissant Parc Chateau and Seville Storm Sewer (FY04) Project in easement acquisition. Anticipate board introduction in August 2004. $92 ,000
Kirkwood Kirkwood Road - Commerce -Reardon (GCKC-140) Phase II (FY02) Delayed due to review time of the Missouri Department of Natural Resources. Currently in easement acquisition. Anticipate board introduction in March 2005. $860,000
Rock Hill Des Peres - Twinbrook Storm Channel (DCSD-190) Local Sewers (FY04) This project is being administered by the city of Rock Hill. City does not plan on bidding the construction contract until January 2005. $85,000
Various Hanley Industrial Court and West Point Drive Phase II (DCBC-150) (FY02) Selection of property acquisition consultant required before appropriation of buyout funds. Anticipate board approval of appropriation in November 2004. $664,000
TOTAL $1,991,000

By Project
Project

Municipality

Reason Continued Cost Est.
Des Peres - Twinbrook Storm Channel (DCSD-190) Local Sewers (FY04) Rock Hill This project is being administered by the city of Rock Hill. City does not plan on bidding the construction contract until January 2005. $85,000
Eulalie Ave. 8600 Block Phase II (FY04) Brentwood Project in easement acquisition. Anticipate board introduction in March 2005. $290,000
Hanley Industrial Court and West Point Drive Phase II (DCBC-150) (FY02) Various Selection of property acquisition consultant required before appropriation of buyout funds. Anticipate board approval of appropriation in November 2004. $664,000
Kirkwood Road - Commerce -Reardon (GCKC-140) Phase II (FY02) Kirkwood Delayed due to review time of the Missouri Department of Natural Resources. Currently in easement acquisition. Anticipate board introduction in March 2005. $860,000
Parc Chateau and Seville Storm Sewer (FY04) Florissant Project in easement acquisition. Anticipate board introduction in August 2004. $92 ,000
TOTAL $1,991,000