CIRP 2005 Infrastructure Continued Projects
By Municipality

Municipality

Project

Reason Continued Cost Est.
Chesterfield Infrastructure Repair #087P Caulks Creek "A" (P-750) Phase IV, Section A (FY04) Project in easement acquisition. Condemnation may be required. Anticipate board introduction in January 2005. $1,600,000
Chesterfield Infrastructure Repair #087P Caulks Creek "A" (P-750) Phase IV, Section B (FY04) Redesign required due to improvements being made by the Monarch-Chesterfield Levee District $3,400,000
Fenton Black Oak & White Birch Court Sanitary Relief (FY04) Project in easement acquisition. Anticipate board introduction in January 2005. $300,000
Kirkwood Upper Sugar Creek Sanitary Relief Sec. C Phase I (FY02) Project in easement acquisition. Construction schedule to be coordinated so work through golf course occurs in winter months. Anticipate board introduction in September 2004. $400,000
Maryland Heights FF-15 McKelvey/R.R. to Adie Sanitary Relief Phase I (FY02) Project in easement acquisition. Anticipate board introduction in March 2005. $1,500,000
Maryland Heights FF-15 McKelvey/R.R. to Adie Sanitary Relief Phase II (FY04) Project in easement acquisition. Anticipate board introduction in March 2005. $2,500,000
St. Louis City Grand and Bates Relief Phase II - Local Sewers (St. Louis CSO Project) (FY04) Project design was administered by U.S. Army Corps of Engineers. District has assumed responsibility for construction due to lack of adequate federal appropriation of funds. Anticipate board introduction in February 2005. $2,500,000
St. Louis City Harlem - Baden Relief Phase III (Broadway) (FY04) Project in easement and property acquisition. Anticipate board introduction in February 2005. $1,500,000
St. Louis City Harlem - Baden Relief Phase III (Highland) (FY04) Design required more time than originally planned. Anticipate board introduction in February 2005. $1,500,000
St. Louis City Laclede's Landing Inflow Reduction (Franklin Drop Shaft) (FY04) Project delayed pending approval by the city of St. Louis. Anticipate board introduction in March 2005. $665,000
St. Louis City Rhodes Avenue Relief Sewer (FY04) Project in easement acquisition. Anticipate board introduction in March 2005. $340,000
St. Louis City Sewer Improvements in St. Louis City Parks Phase IIA (FY04) Delayed so construction activities would not disrupt 2004 Celebration events at Forest Park.  Anticipate board introduction in September 2004. $515,000
Town and Country Oak Drive to Bopp Lane Sanitary Relief Phase II (FY04) Waiting for completion of Phase I construction and Phase II easement acquisition. Anticipate board introduction in March 2005. $750,000
Unincorporated Coldwater Sanitary Relief Section A, Phase I (FY04) Delayed due to adjustments in design flows. Anticipated board introduction in September 2004. $6,300,000
Unincorporated Fishpot East Sanitary Relief Phase III (FY04) Project in easement acquisition. Condemnation may be required. Anticipate board introduction in March 2005. $1,800,000
Unincorporated Lower Meramec River Wastewater Treatment Plant Electrical Supply (FY04) Delayed due to need for Ameren to provide cost for secondary power feed. Anticipate board introduction in September 2004. $3,900,200
Unincorporated Lower Meramec River Wastewater Treatment Plant Wetlands Mitigation Phase II (FY04) Need for additional wetland mitigation has not been determined. Anticipate board introduction in May 2005. $130,200
Unincorporated Towne South Interceptor Sanitary Relief Phase II (FY02) Project in easement acquisition. Condemnation will be required. Anticipate board introduction in May 2005. $3,000,000
Valley Park Grand Glaize Treatment Plant (Land Acquisition) (FY04) Selection of property acquisition consultant required before appropriation of land acquisition funds. Anticipate board introduction in February 2005. $750,000
    TOTAL $33,050,200

By Project

Project

Municipality

Reason Continued Cost Est.
Black Oak & White Birch Court Sanitary Relief (FY04) Fenton Project in easement acquisition. Anticipate board introduction in January 2005. $300,000
Coldwater Sanitary Relief Section A, Phase I (FY04) Unincorporated Delayed due to adjustments in design flows. Anticipated board introduction in September 2004. $6,300,000
FF-15 McKelvey/R.R. to Adie Sanitary Relief Phase I (FY02) Maryland Heights Project in easement acquisition. Anticipate board introduction in March 2005. $1,500,000
FF-15 McKelvey/R.R. to Adie Sanitary Relief Phase II (FY04) Maryland Heights Project in easement acquisition. Anticipate board introduction in March 2005. $2,500,000
Fishpot East Sanitary Relief Phase III (FY04) Unincorporated Project in easement acquisition. Condemnation may be required. Anticipate board introduction in March 2005. $1,800,000
Grand and Bates Relief Phase II - Local Sewers (St. Louis CSO Project) (FY04) St. Louis City Project design was administered by U.S. Army Corps of Engineers. District has assumed responsibility for construction due to lack of adequate federal appropriation of funds. Anticipate board introduction in February 2005. $2,500,000
Grand Glaize Treatment Plant (Land Acquisition) (FY04) Valley Park Selection of property acquisition consultant required before appropriation of land acquisition funds. Anticipate board introduction in February 2005. $750,000
Harlem - Baden Relief Phase III (Broadway) (FY04) St. Louis City Project in easement and property acquisition. Anticipate board introduction in February 2005. $1,500,000
Harlem - Baden Relief Phase III (Highland) (FY04) St. Louis City Design required more time than originally planned. Anticipate board introduction in February 2005. $1,500,000
Infrastructure Repair #087P Caulks Creek "A" (P-750) Phase IV, Section A (FY04) Chesterfield Project in easement acquisition. Condemnation may be required. Anticipate board introduction in January 2005. $1,600,000
Infrastructure Repair #087P Caulks Creek "A" (P-750) Phase IV, Section B (FY04) Chesterfield Redesign required due to improvements being made by the Monarch-Cheaterfield Levee District $3,400,000
Laclede's Landing Inflow Reduction (Franklin Drop Shaft) (FY04) St. Louis City Project delayed pending approval by the city of St. Louis. Anticipate board introduction in March 2005. $665,000
Lower Meramec River Wastewater Treatment Plant Electrical Supply (FY04) Unincorporated Delayed due to need for Ameren to provide cost for secondary power feed. Anticipate board introduction in September 2004. $3,900,200
Lower Meramec River Wastewater Treatment Plant Wetlands Mitigation Phase II (FY04) Unincorporated Need for additional wetland mitigation has not been determined. Anticipate board introduction in May 2005. $130,200
Oak Drive to Bopp Lane Sanitary Relief Phase II (FY04) Town and Country Waiting for completion of Phase I construction and Phase II easement acquisition. Anticipate board introduction in March 2005. $750,000
Rhodes Avenue Relief Sewer (FY04) St. Louis City Project in easement acquisition. Anticipate board introduction in March 2005. $340,000
Sewer Improvements in St. Louis City Parks Phase IIA (FY04) St. Louis City Delayed so construction activities would not disrupt 2004 Celebration events at Forest Park.  Anticipate board introduction in September 2004. $515,000
Towne South Interceptor Sanitary Relief Phase II (FY02) Unincorporated Project in easement acquisition. Condemnation will be required. Anticipate board introduction in May 2005. $3,000,000
Upper Sugar Creek Sanitary Relief Sec. C Phase I (FY02) Kirkwood Project in easement acquisition. Construction schedule to be coordinated so work through golf course occurs in winter months. Anticipate board introduction in September 2004. $400,000
    TOTAL $33,050,200