| CIRP 2005 Infrastructure Continued Projects |
| Municipality |
Project |
Reason
Continued |
Cost
Est. |
|
Chesterfield |
Infrastructure Repair #087P Caulks Creek "A" (P-750) Phase IV, Section
A (FY04) |
Project in easement acquisition. Condemnation may be required. Anticipate
board introduction in January 2005. |
$1,600,000 |
|
Chesterfield |
Infrastructure Repair #087P Caulks Creek "A" (P-750) Phase IV, Section
B (FY04) |
Redesign required due to improvements being made by the Monarch-Chesterfield
Levee District |
$3,400,000 |
|
Fenton |
Black Oak & White Birch Court Sanitary Relief (FY04)
|
Project in easement acquisition. Anticipate board introduction in January
2005. |
$300,000 |
|
Kirkwood |
Upper Sugar Creek Sanitary Relief Sec. C Phase I (FY02)
|
Project in easement acquisition. Construction
schedule to be coordinated so work through golf course occurs in winter
months.
Anticipate board introduction in September 2004. |
$400,000 |
|
Maryland Heights |
FF-15 McKelvey/R.R. to Adie Sanitary Relief
Phase I (FY02) |
Project in easement acquisition. Anticipate board introduction in March
2005. |
$1,500,000 |
|
Maryland Heights |
FF-15 McKelvey/R.R. to Adie Sanitary Relief
Phase II (FY04) |
Project in easement acquisition. Anticipate board introduction in March
2005. |
$2,500,000 |
|
St. Louis City |
Grand and Bates Relief Phase II - Local Sewers (St. Louis CSO Project)
(FY04) |
Project design was administered by U.S. Army Corps of Engineers. District
has assumed responsibility for construction due to lack of adequate
federal appropriation of funds. Anticipate board introduction in February
2005. |
$2,500,000 |
|
St. Louis City |
Harlem - Baden Relief Phase III (Broadway) (FY04) |
Project in easement and property acquisition. Anticipate board introduction
in February 2005. |
$1,500,000 |
|
St. Louis City |
Harlem - Baden Relief Phase III (Highland) (FY04) |
Design required more time than originally planned. Anticipate board
introduction in February 2005. |
$1,500,000 |
|
St. Louis City |
Laclede's Landing Inflow Reduction (Franklin Drop Shaft) (FY04)
|
Project delayed pending approval by the city of St. Louis. Anticipate
board introduction in March 2005. |
$665,000 |
|
St. Louis City |
Rhodes Avenue Relief Sewer (FY04) |
Project in easement acquisition. Anticipate board introduction in March
2005. |
$340,000 |
|
St. Louis City |
Sewer Improvements in St. Louis City Parks Phase IIA (FY04)
|
Delayed so construction activities would not disrupt 2004 Celebration
events at Forest Park. Anticipate board introduction in September 2004.
|
$515,000 |
|
Town and Country |
Oak Drive to Bopp Lane Sanitary Relief Phase II (FY04)
|
Waiting for completion of Phase I construction and Phase II easement
acquisition. Anticipate board introduction in March 2005.
|
$750,000 |
|
Unincorporated |
Coldwater Sanitary Relief Section A, Phase
I (FY04) |
Delayed due to adjustments in design flows. Anticipated board introduction
in September 2004. |
$6,300,000 |
|
Unincorporated |
Fishpot East Sanitary Relief Phase III (FY04) |
Project in easement acquisition. Condemnation may be required. Anticipate
board introduction in March 2005. |
$1,800,000 |
|
Unincorporated |
Lower Meramec River Wastewater Treatment
Plant Electrical Supply (FY04) |
Delayed due to need for Ameren to provide
cost for secondary power feed.
Anticipate board introduction in September 2004. |
$3,900,200 |
|
Unincorporated |
Lower Meramec River Wastewater Treatment
Plant Wetlands Mitigation Phase II (FY04) |
Need for additional wetland mitigation has not been determined.
Anticipate board introduction in May 2005. |
$130,200 |
|
Unincorporated |
Towne South Interceptor Sanitary Relief Phase II (FY02)
|
Project in easement acquisition. Condemnation will be required. Anticipate
board introduction in May 2005. |
$3,000,000 |
|
Valley Park |
Grand Glaize Treatment Plant (Land Acquisition) (FY04)
|
Selection of property acquisition consultant required before appropriation
of land acquisition funds. Anticipate board introduction in February
2005. |
$750,000 |
| |
|
TOTAL |
$33,050,200 |
| Project
|
Municipality |
Reason
Continued |
Cost
Est. |
|
Black Oak & White Birch Court Sanitary Relief (FY04)
|
Fenton |
Project in easement acquisition. Anticipate board introduction in January
2005. |
$300,000 |
|
Coldwater Sanitary Relief Section A, Phase
I (FY04) |
Unincorporated |
Delayed due to adjustments in design flows. Anticipated board introduction
in September 2004. |
$6,300,000 |
|
FF-15 McKelvey/R.R. to Adie Sanitary Relief
Phase I (FY02) |
Maryland Heights |
Project in easement acquisition. Anticipate board introduction in March
2005. |
$1,500,000 |
|
FF-15 McKelvey/R.R. to Adie Sanitary Relief
Phase II (FY04) |
Maryland Heights |
Project in easement acquisition. Anticipate board introduction in March
2005. |
$2,500,000 |
|
Fishpot East Sanitary Relief Phase III (FY04) |
Unincorporated |
Project in easement acquisition. Condemnation may be required. Anticipate
board introduction in March 2005. |
$1,800,000 |
|
Grand and Bates Relief Phase II - Local Sewers (St. Louis CSO Project)
(FY04) |
St. Louis City |
Project design was administered by U.S. Army Corps of Engineers. District
has assumed responsibility for construction due to lack of adequate
federal appropriation of funds. Anticipate board introduction in February
2005. |
$2,500,000 |
|
Grand Glaize Treatment Plant (Land Acquisition) (FY04)
|
Valley Park |
Selection of property acquisition consultant required before appropriation
of land acquisition funds. Anticipate board introduction in February
2005. |
$750,000 |
|
Harlem - Baden Relief Phase III (Broadway) (FY04) |
St. Louis City |
Project in easement and property acquisition. Anticipate board introduction
in February 2005. |
$1,500,000 |
|
Harlem - Baden Relief Phase III (Highland) (FY04) |
St. Louis City |
Design required more time than originally planned. Anticipate board
introduction in February 2005. |
$1,500,000 |
|
Infrastructure Repair #087P Caulks Creek "A" (P-750) Phase IV, Section
A (FY04) |
Chesterfield |
Project in easement acquisition. Condemnation may be required. Anticipate
board introduction in January 2005. |
$1,600,000 |
|
Infrastructure Repair #087P Caulks Creek "A" (P-750) Phase IV, Section
B (FY04) |
Chesterfield |
Redesign required due to improvements being made by the Monarch-Cheaterfield
Levee District |
$3,400,000 |
|
Laclede's Landing Inflow Reduction (Franklin Drop Shaft) (FY04)
|
St. Louis City |
Project delayed pending approval by the city of St. Louis. Anticipate
board introduction in March 2005. |
$665,000 |
|
Lower Meramec River Wastewater Treatment
Plant Electrical Supply (FY04) |
Unincorporated |
Delayed due to need for Ameren to provide
cost for secondary power feed.
Anticipate board introduction in September 2004. |
$3,900,200 |
|
Lower Meramec River Wastewater Treatment
Plant Wetlands Mitigation Phase II (FY04) |
Unincorporated |
Need for additional wetland mitigation has not been determined.
Anticipate board introduction in May 2005. |
$130,200 |
|
Oak Drive to Bopp Lane Sanitary Relief Phase II (FY04)
|
Town and Country |
Waiting for completion of Phase I construction and Phase II easement
acquisition. Anticipate board introduction in March 2005.
|
$750,000 |
|
Rhodes Avenue Relief Sewer (FY04) |
St. Louis City |
Project in easement acquisition. Anticipate board introduction in March
2005. |
$340,000 |
|
Sewer Improvements in St. Louis City Parks Phase IIA (FY04)
|
St. Louis City |
Delayed so construction activities would not disrupt 2004 Celebration
events at Forest Park. Anticipate board introduction in September 2004.
|
$515,000 |
|
Towne South Interceptor Sanitary Relief Phase II (FY02)
|
Unincorporated |
Project in easement acquisition. Condemnation will be required. Anticipate
board introduction in May 2005. |
$3,000,000 |
|
Upper Sugar Creek Sanitary Relief Sec. C Phase I (FY02)
|
Kirkwood |
Project in easement acquisition. Construction
schedule to be coordinated so work through golf course occurs in winter
months.
Anticipate board introduction in September 2004. |
$400,000 |
| |
|
TOTAL |
$33,050,200 |
Posted 07/04
|